The Party Wall Act In Plain English

Last Updated: September 29, 2026

Table of Contents

The Party Wall Act Explained

The Party Wall Act is a piece of legislation and, as such, is hard to comprehend and is full of complications. It is easy to make errors, and there are many points that cause misunderstanding.

  • The Act is about three things: building on or near a boundary, working on an existing party wall or party structure, and excavating close to neighbouring buildings.
  • Not every project needs the same notice: loft conversions, extensions, basement works, and deeper foundations often trigger formal notice requirements under sections 1, 3 or 6.
  • If your neighbour does not consent, that does not automatically stop the work: it usually means a dispute is deemed to have arisen and the matter moves into the surveyor process under section 10, where an award sets out how the work can proceed.
  • The building owner usually bears the main risks and costs: they pay for the works they want, must avoid unnecessary inconvenience, may have to compensate for damage, must properly provide access arrangements, and sometimes give security for expenses.

The Act sets legal rules for:

  • Building on or near a boundary.
  • Working on an existing party wall or party structure.
  • Excavating near neighbouring buildings.
  • Resolving disputes between neighbours when this kind of work is proposed.

Know your way around the Act. Here is a list of all 22 Sections and what they concern.

  1. Rules for new boundary walls.
  2. Rights to work on an existing party wall/structure.
  3. Notice requirements for party structure works.
  4. Neighbour’s counter-notice rights.
  5. When a dispute is deemed to arise.
  6. Rules for excavation near neighbouring buildings.
  7. Compensation and duties when doing the work.
  8. Rights to enter neighbouring land.
  9. Easements still matter.
  10. Surveyor-based dispute resolution.
  11. Who pays for what?
  12. Security for expenses.
  13. Accounting for recoverable costs.
  14. Payment of sums due.
  15. How notices are served.
  16. Offences for obstruction etc.
  17. Recovery of money as civil debt.
  18. Special historic exemptions.
  19. Application to Crown land.
  20. Definitions.
  21. Supplementary statutory powers.
  22. Name, start date, and extent of the Act.

Westville Associates has been through the Act and translated it into plain English

Section 1 – New building on line of junction

This covers the construction of a new wall along the boundary line between two properties.

In practice, it says:

  • You can build up to the boundary.
  • You usually cannot build astride the boundary without the adjoining owner’s consent.
  • If you want to build a wall wholly on your own land at the line of junction, you must generally serve notice first.
  • Special rules apply where foundations project under neighbouring land.

This is the starting point for boundary-wall projects. Pages 3–4.

Section 2 – Repair etc. of party wall: rights of owner

This is one of the core sections. It gives a building owner the right to do certain works to an existing party wall, party structure, or party fence wall.

Typical permitted works include:

  • Repairing, underpinning, thickening, raising, or demolishing and rebuilding a party wall.
  • Cutting into the wall.
  • Inserting beams, flashings, damp-proof courses, and similar items.
  • Cutting away projections.
  • Demolishing parts that are defective.
  • Raising or extending a wall where needed.
  • Exposing a wall that was previously enclosed, subject to weatherproofing.

It also limits these rights:

  • The works must be necessary or permitted by the Act.
  • Damage to the neighbour’s property should be avoided or made good.
  • Extra burdens cannot simply be imposed without following the Act.

Section 3 – Party structure notices

Before exercising many rights under section 2, the building owner must serve a notice on the adjoining owner.

The notice should state things like:

  • The building owner’s name and address.
  • The works proposed.
  • Plans/sections/details where special foundations or similar matters are involved.
  • The intended start date.

The notice normally must be served at least two months before the work starts, and it lapses if the work does not begin within the specified period. Pages 6–7.

Section 4 – Counter notices

The adjoining owner can respond with a counter-notice.

This allows them to say, in effect:

“If you are doing this work, you must also do certain additional works for my benefit,” provided those additional works are reasonably required.

This section is important because it prevents one-sided arrangements and lets the neighbour protect their own property interests.

Section 5 – Disputes arising under sections 3 and 4

If:

  • The adjoining owner consents, the work can usually proceed; but
  • if they do not consent within the statutory period, or a disagreement arises,

Then a dispute is deemed to have arisen.

That deemed dispute triggers the surveyor procedure later in section 10. Page 7.

Section 6 – Adjacent excavation and construction

This governs excavation near neighbouring buildings or structures.

It applies where someone plans to excavate:

  • within 3 metres of a neighbouring structure and deeper than its foundations, or
  • within 6 metres in certain deeper excavation cases, based on a notional 45-degree line.

The building owner must serve notice describing:

  • the proposed excavation,
  • the site,
  • and depth/details, often with plans.

If the neighbour dissents or does not respond, the matter goes into dispute resolution. This is the section most often raised on basement digs and extension foundations close to next door.

Section 7 – Compensation etc.

This says a building owner exercising rights under the Act must:

  • not cause unnecessary inconvenience, and
  • compensate for loss or damage caused by the works.

It also makes clear:

  • statutory rights under the Act do not override every other legal protection,
  • works still need to be executed properly,
  • and owners remain responsible for the consequences of their operations.

Section 8 – Rights of entry

This gives the building owner and those working for them a limited right to enter adjoining land or premises where necessary to carry out works authorised by the Act.

But:

  • notice normally has to be given (at least 14 days, except in an emergency),
  • Entry must be during usual working hours,
  • force is limited and there are rules for emergencies and for when premises are closed.

This section exists because some lawful party wall work cannot be carried out from only one side. Pages 9–10.

Section 9 – Easements

This section says the Act does not authorise interference with easements, such as rights of light or other property rights, except as specifically provided.

So even where party wall rights exist, they do not automatically wipe out other legal rights over land.

Section 10 – Resolution of disputes

This is the Act’s main dispute-resolution mechanism.

If a dispute arises:

  • The parties may appoint one agreed surveyor, or
  • Each may appoint their own surveyor.

Those surveyors must then select a third surveyor.

The surveyor(s) determine matters in dispute and make an award, which can deal with:

  • the right to do the work, how and when it is done,
  • safeguards, compensation, access and costs.

The award is binding unless appealed to the county court within 14 days of it being served.

Section 11 – Expenses

This explains who pays.

The basic idea is:

  • The building owner usually pays for the work they want,
  • But where work benefits both parties, or repairs a defect for which both are responsible, costs may be shared,
  • And where one owner makes greater use of a wall or structure, that can affect the contribution.

This section is detailed because it addresses many different scenarios: repairs, rebuilding, raising walls, enclosing land, later use of a wall, and so on. Pages 12–13.

Section 12 – Security for expenses

In some circumstances, the adjoining owner can require the building owner to provide security for expenses before works begin.

This is a financial safeguard. It helps protect the neighbour if:

  • works start but are not completed properly, or
  • money may later be needed to make good damage or complete protective measures.

Section 13 – Account for work carried out

Where the adjoining owner is liable to contribute to expenses, the building owner must provide an account showing:

  • the work done, the costs,
  • deductions or payments already made and supporting detail.

The adjoining owner can object within the statutory time. This section is essentially about transparency in cost recovery.

Section 14 – Settlement of account

Any amount due from the adjoining owner under section 13 must then be paid in accordance with the account served, subject to any valid objection or dispute process. This is the short follow-on provision that turns the accounting exercise into an enforceable payment position.

Section 15 – Service of notices etc.

This explains how notices and documents are legally served under the Act.

Service can usually be provided by:

  • delivering personally,
  • leaving at the proper address,
  • posting, or email where the recipient has agreed to receive notices electronically,
  • or serving a body corporate at its office.

It also provides alternatives when the owner’s name or address is unknown.

Section 16 – Offences

This creates offences for improper obstruction or interference.

For example:

  • refusing access when someone is entitled to enter under the Act,
  • or obstructing a person exercising statutory rights.

This gives some legal teeth to the access and compliance provisions. Page 15.

Planning party wall work in Surrey or London? Ask for a quote and we’ll guide you through the Act.

Section 17 – Recovery of sums

Any money payable under the Act may be recovered summarily as a civil debt.

That means unpaid sums can be pursued through normal debt-recovery channels rather than the Act needing a special collection mechanism.

Section 18 – Exception in case of Temples etc.

Not important

Section 19 – The Crown

This explains how the Act applies to Crown land. Not important

Section 20 – Interpretation

This is the definitions section.

It explains what important terms mean, including:

  • adjoining owner and adjoining occupier
  • appointing officer and building owner
  • foundations, owner, party fence wall, party structure, party wall,
  • special foundations, surveyor.

This section matters.

Section 21 – Other statutory provisions

Not important

Section 22 – Short title, commencement and extent

Not important

Next Step

If you would like to talk to Simon about your party wall, then please contact him here or simply call 07834 761 411. We cover all of Surrey, Hampshire and London.

Our Lead Surveyor

Simon Burrage surveyor

While I specialise in building surveys and party wall work, I can also assist with a range of other survey services. I work with Architects, homeowners, and Landlords across Surrey and London. I have over 10 years of experience and have many clients who have been using me for years. I look forward to meeting new clients and am passionate about helping them solve any issues their new property may have.

Get a Quote

GDPR
Google
Chris Thoume profile picture
Chris Thoume
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Great experience working with Simon: he took me through the process in simple terms and was always willing to provide considered pragmatic advice.
Google
Jessica Sanzone profile picture
Jessica Sanzone
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Would highly recommend using Westville Associates. Appointed Brett to act for us in regards to some party wall matters. We found him to be polite and professional with a wealth of knowledge in this field. Great communication throughout the process. Great service from start to finish.
Google
Kate Rennie profile picture
Kate Rennie
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
I was recommended to use Westville Associates through a colleague to carry out a survey of a house we were looking to purchase. I couldn’t have been happier with the whole process. From start to finish, Simon was professional, punctual, through and gave good advice with issues that arose from the survey. I have and will continue to recommend Westville Associates to anyone wishing to carry out any surveys.
Google
Niki Yazdanian profile picture
Niki Yazdanian
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Simon carried out a full building survey for us on a property in Oxted. We found him to be prompt, professional, very knowledgeable, a great service all round. We would have no hesitation in recommending him and using him again.
Google
Sophie Beed profile picture
Sophie Beed
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Really recommend Westville, great communication and advice. Clear, concise and quick report and more than happy to discuss any points to help us understand our purchase better.
Google
Sara Mahdavian profile picture
Sara Mahdavian
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
We used Wesville Associates for a full Building Survey for our property in Claygate after a recommendation from a friend. Simon was very personable, knowledgable and professional, and was able to work around our tight timeframe. We felt in good hands from the start!
Google
WashPod profile picture
WashPod
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
“Westville Associates undertook a homebuyers report for us prior to the purchase of our flat in Wandsworth. The service from start to finish was exemplary. Simon booked us in, undertook the inspection and presented the report to us all within 7 working days which was appreciated as time was against us somewhat. The after sales care was also great as we had several questions about the property that were dealt with over the phone. Friendly, professional and prompt service. Would definitely recommend. Rob.”
Google
Craig C profile picture
Craig C
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
I have worked in Surbiton and the surrounding areas as an agent for over 10 years and could not recommend Simon highly enough. He has a wealth of knowledge and goes above and beyond to ensure his clients fully understand the fantastic reports he creates, unlike many other surveyors who just send a confusing report without further explanation of key points. I am so pleased Simon has set up his solo venture - Westville Associates and will be recommending him to all of my clients.